Crysbol Consulting provides professional geotechnical investigations, geophysical surveys, groundwater exploration and drilling services in Amersfoort and surrounding areas. Our experienced technical teams are equipped to undertake projects of varying sizes, delivering reliable site investigations and practical solutions tailored to each client's requirements.

Amersfoort is a small farming town on the southern Highveld, with maize, cattle and sheep on the surrounding farms. Eskom's Majuba power station lies between Amersfoort and Volksrust.

From Amersfoort we also cover Perdekop.

Ground conditions in Amersfoort

  1. Split seams and dolerite

    Around Majuba, a coal seam roughly 3.5 metres thick at about 300 metres depth was disrupted by frequent dolerite intrusions. Close-spaced drilling and careful structural interpretation are needed before a coal project here can be planned.

  2. Ash and coal stockpiles

    Ash disposal and coal handling at a large power station can release salts into shallow groundwater and streams, so monitoring boreholes and surface water sampling are long-term requirements.

When you need it

When you need yield testing in Amersfoort

  • You have a new borehole and need to size the pump correctly
  • A bank, buyer or municipality asks for a borehole certificate
  • You plan to supply irrigation, a school, a clinic or an estate from the borehole
  • An existing borehole's yield has dropped or it pumps dry

How it works

Our process, step by step

  1. 01

    Checks and calibration

    We measure the depth, rest water level and condition of the borehole, then run a short calibration test to set the pumping rates.

  2. 02

    Step-drawdown tests

    Three to four steps at increasing pumping rates, each lasting 60 minutes, show how the water level responds to demand.

  3. 03

    Constant discharge test

    Pumping at a steady rate for 24 hours shows how the borehole and aquifer behave over time. A groundwater sample is taken during this test.

  4. 04

    Recovery measurements

    After each test, we record how quickly the water level recovers once pumping stops.

  5. 05

    Analysis and certificate

    We analyse the data and issue a borehole yield certificate with the sustainable yield, pump depth and pumping schedule, together with the water quality results.

Recent projects

Borehole yield testing in Mpumalanga: recent work

  • Thembisile Hani Local Municipality, Mpumalanga · June 2026

    24-hour borehole yield test at Tjhidelani Primary School

    A 24-hour borehole yield test at Tjhidelani Primary School, with step-drawdown, constant-rate and recovery testing.

Questions

Borehole yield testing in Amersfoort: questions

Do you offer borehole yield testing in Amersfoort?

Yes. Yield testing for farms, lodges and rural water schemes in the Lowveld. Crysbol Consulting provides professional geotechnical investigations, geophysical surveys, groundwater exploration and drilling services in Amersfoort and surrounding areas. Our experienced technical teams are equipped to undertake projects of varying sizes, delivering reliable site investigations and practical solutions tailored to each client's requirements.

How do I get a quote for yield testing work in Amersfoort?

Send us the site location and a short description of the work through our quote form, or call 010 102 3591. We usually reply with a scope and a quote within two working days.

How long does a borehole yield test take?

A standard test includes three to four 60-minute step-drawdown tests and a 24-hour constant discharge test, with recovery measured after each, so the field work usually runs over two days.

What does a borehole certificate show?

It records the borehole's depth and construction, the test results, the recommended sustainable yield, the depth to install the pump and a daily pumping schedule. If we sample the water, results against SANS 241 are included.

Need yield testing in Amersfoort?

Send us the site location and what you need. We plan field work to cover several sites per trip and usually reply with a scope and quote within two working days.